2020-11-02 Gumzo ya Mwezi
Gumzo ya Mwezi
The monthly chat (kiswaheli: gumzo ya mwezi) will help the developer teams to show-case their achievements to the developers committee and to interested members of the implementers committee. The gumzo is oriented at Scrum review sessions: let's celebrate the achievements of the past month!
Co-ordinates
Date: 02.11.2020
Time: 11:00 am (UCT)
Room: https://meet.jit.si/openIMISDevelopers - kindly indicate your name and organisation (jitsi claims to support Chrome, Chromium & MS Edge and Firefox browsers only. You might also want to try the jitsi app)
Participants: (kindly only add yourself, not others):
@Uwe Wahser
@Laure Pontis
@Dragos Dobre
@Simona Dobre
@Patrick Delcroix
Schedule
The call is specifically addressed to the Developers Committee and the Implementers Committee. Each session consists of 10 minutes presentation plus 5 minutes Q&A - please have your bio breaks before the event
Please prepare your presentations with an eye on:
what did we achieve last month
where are problems
where do we want to go next month
rough estimation on the remaining time budget and workload
When (UCT) | Duration | Who | Topic |
---|---|---|---|
11:00 (UCT) | 10 + 5 min | @Uwe Wahser | Welcome note, overview & current topics |
11:15 (UCT) | 10 + 5 min | 3rd Level support and release planning | |
11:30 (UCT) | 10 + 5 min | Notice D.1: AI | |
11:45 (UCT) | 10 + 5 min | Notice D.1: Beneficiaries, Policies, Contributions | |
12:00 (UCT) | 10 + 5 min | Notice D.1: Formal Sector | |
12:15 (UCT) | 10 + 5 min | Healthix | Notice D.1: Formal Sector APIs |
12:30 (UCT) | 10 + 5 min |
|
|
12:45 (UCT) | 10 + 5 min |
|
|
Minutes
GIZ
SwissTPH - 3rd Level support and release planning
Presentation:
Time budget remaining and workload remaining: 240md (100%)
Discussion:
October 2020 Release to be finalized
SwissTPH - Notice D.1: AI
Presentation:
Time budget remaining and workload remaining:
Discussion:
updated documentation of the process: openIMIS AI-based Claim Adjudication
BlueSquare - Notice D1: Beneficiaries, Policies, Contributions
Presentation:
Time budget and workload remaining:
Iteration 1: Dev readiness - 24.5 m/d (on 20) : 4.5 overrun (-> iteration 5 contingency) - closed
Iteration 2: Insurees & Families - 50 m/d (on 50) - continued module implementation - closed
Iteration 3: Policies - 21 m/d (50 m/d) deadline 30/11
Iteration 4: Contributions - (50 m/d) - deadline 31/01
Iteration 5: Closure - (20 m/d -> 15.5 m/d) - deadline 28/02
Discussion:
Workshop 19.11 10am - 12am
Please confirm attendance on the doodle https://doodle.com/poll/fs389g77yn686euz?utm_source=poll&utm_medium=link
SwissTPH - Notice D.1: Formal Sector
Presentation:
Status / Remaining budget:
Remaining deliverables:
Discussion:
Healthix - Notice D.1: Formal Sector API
Presentation: not available
Time budget remaining and workload remaining:
Discussion:
Other Topics
Evaluation
Please fill the evaluation form after every call (see link in top ). The results will be updated here, if there is sufficient feedback: