The monthly chat (kiswaheli: gumzo ya mwezi) will help the developer teams to show-case their achievements to the developers committee and to interested members of the implementers committee. The gumzo is oriented at Scrum review sessions: let's celebrate the achievements of the past month!
Co-ordinates
Date: 06.04.2020
Time: 11:00 am (GMT)
Room: https://meet.jit.si/openIMISDevelopers - kindly indicate your name and organisation (jitsi claims to support Chrome, Chromium and Firefox browsers only. However - screen sharing caused problems on Firefox recently. You might also want to try the jitsi app)
Participants: (kindly only add yourself, not others):
@Uwe Wahser
@Purushottam Sapkota
@Dragos Dobre
@Patrick Delcroix
@Xavier Gillmann (Unlicensed)
@Fourie, Carl
@Siddharth Srivastava
Schedule
The call is specifically addressed to the Developers Committee and the Implementers Committee. Each session consists of 10 minutes presentation plus 5 minutes Q&A - please have your bio breaks before the event
Please prepare your presentations with an eye on:
what did we achieve last month
where are problems
where do we want to go next month
rough estimation on the remaining time budget and workload
When (GMT) | Duration | Who | Topic |
---|---|---|---|
11:00 | 10 + 5 min | @Uwe Wahser | Welcome note, overview & current topics |
11:15 | 10 + 5 min | 3rd Level support and release planning | |
11:30 | 10 + 5 min | Re-architecturing | |
11:45 | 10 + 5 min | DHIS2 Integration |
Minutes
GIZ
Welcome
SwissTPH
Presentation: SwissTPH openIMIS March 2020.pptx
Time budget remaining and workload remaining: 20 d
Discussion:
issues “Resolved”: can they be closed after a warning to the requester?
issue “Waiting for Customer”: send a reminder after 2 weeks?
DB migration: new issue on “bundled services“ with DB modification
BlueSquare
Presentation: openIMIS - Gumzo ya Mwezi - 2020-04-06.pdf
Time budget and workload remaining:
Iteration 1 (FHIR API) - 56,5 / 60 m/d CLOSED
Iteration 2 (All proxy frontend)- 18,5 / 20 m/d CLOSED
Iteration 3 (Claim module) - 144 m/d on 90 m/d reopened and CLOSED again
Iteration 4 (Locations) - 16,5 m/d on 20 m/d reopened and CLOSED again
Closing & extensions: - 11,5 m/d on 4,5 m/d, CLOSED
Discussion:
247 m/d (7 m/d overbudget)
Finishing FHIR API fine grained (2-3 m/d, as advance on next contract)
Final bug fixes (limits & ceilings)
Closing report
Tabbing issue:
HISP India
Presentation:
Time budget & workload remaining:
Discussion:
Other Topics
include SwissTPH students in monthly Gumzo presentations
provide budget for on boarding of new developers