2021-07-05 Gumzo ya Mwezi
Gumzo ya Mwezi
The monthly chat (kiswaheli: gumzo ya mwezi) will help the developer teams to show-case their achievements to the developers committee and to interested members of the implementers committee. The gumzo is oriented at Scrum review sessions: let's celebrate the achievements of the past month!
Co-ordinates
Date: 07.06.2021
Time: 11:00 am (UTC)
Room: https://meet.jit.si/openIMISDevelopers - kindly indicate your name and organisation (jitsi claims to support Chrome, Chromium & MS Edge and Firefox browsers only. You might also want to try the jitsi app)
Participants: (kindly only add yourself, not others):
@Uwe Wahser
@Dragos Dobre
@Eric Darchis
@Purushottam Sapkota
@Luciana Rajula
Schedule
The call is specifically addressed to the Developers Committee and the Implementers Committee. Each session consists of 10 minutes presentation plus 5 minutes Q&A - please have your bio breaks before the event
Please prepare your presentations with an eye on:
what did we achieve last month
where are problems
where do we want to go next month
rough estimation on the remaining time budget and workload
When (UTC) | Duration | Who | Topic |
---|---|---|---|
11:00 (UTC) | 10 + 5 min | https://openimis.atlassian.net/wiki/spaces/OP/pages/940048440 | Welcome note, overview & current topics |
11:15 (UTC) | 10 + 5 min | https://openimis.atlassian.net/wiki/spaces/OP/pages/835682333 | https://openimis.atlassian.net/wiki/spaces/OP/pages/2161148020: 3rd Level support and release planning |
11:30 (UTC) | 10 + 5 min | https://openimis.atlassian.net/wiki/spaces/OP/pages/835321877 | https://openimis.atlassian.net/wiki/spaces/OP/pages/2161148040 |
11:45 (UTC) | 10 + 5 min | https://openimis.atlassian.net/wiki/spaces/OP/pages/835682333 | https://openimis.atlassian.net/wiki/spaces/OP/pages/2161148104 |
12:00 (UTC) | 10 + 5 min | @Daniella Majakari (https://openimis.atlassian.net/wiki/spaces/OP/pages/835682333 ) | Capacity building strategy |
Minutes
GIZ
https://openimis.atlassian.net/wiki/spaces/OP/pages/215777296
https://openimis.atlassian.net/wiki/spaces/OP/pages/2058879051
SwissTPH - 3rd Level support and release planning
Presentation:
Time budget remaining and workload remaining: 164 days remaining (68%)
Discussion:
Anniversary release might not be possbile given the diverse summer holidays
BlueSquare - T3: Modular Transformation
Presentation:
Time budget and workload remaining: on track
Discussion:
SwissTPH - Notice E.0: Shelf readiness
Presentation:
Time budget remaining and workload remaining:
Discussion:
1.3. FHIR Authentication
2.1 Docker improvements + Instant OpenHIE Docker packages
Other Topics
Capacity development:
Feedback
Please fill the evaluation form after every call (see link in top ). The results will be updated here, if there is feedback:
Legend
Did you encounter a problem or do you have a suggestion?
Please contact our Service Desk
This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License. https://creativecommons.org/licenses/by-sa/4.0/