The monthly chat (kiswaheli: gumzo ya mwezi) will help the devloper teams to show-case their achievements to the developers committee and to interested members of the implementers committee. The gumzo is oriented at Scrum review sessions: let's celebrate the achievements of the past month!

Co-ordinates

Date: 06.05.2019

Time: 11:00 am (GMT) (Still a bit confused about daylight savings, but I suppose this is the best compromise for all)

Room: https://meet.jit.si/openIMISDevelopers - kindly indicate your name and organisation (jitsi claims to support Chrome, Chromium and Firefox browsers only.  However - screen sharing caused problems on Firefox recently. You might also want to try the jitsi app)

Participants: (kindly only add yourself, not others)

  • @Uwe Wahser

  • @Daniel Futerman (Jembi)

  • @laxman manandhar (Possible)

  • Xavier Gillmann (Bluesquare)

  • @Fourie, Carl (PATH)

  • Alicia Spengler (GIZ)

  • Saurabh (HISP India)

  • @Kamil Madej (Deactivated)

Schedule

After our testrun last month within the developers committee and the co-ordination desk only, we now open it up to the implementers committee as well. Each session is 10 minutes presentation plus 5 minutes Q&A - please have your bio breaks before the event

Please prepare your presentations with an eye on:

  • what did we achieve last month

  • where are problems

  • where do we want to go next month

  • rough estimation on the remaining time budget and workload

When (GMT)

Duration

Who

Topic

When (GMT)

Duration

Who

Topic

11:00

10 + 5 min

@Uwe Wahser

Welcome note, overview & current topics

11:15

10 + 5 min

SwissTPH

3rd Level support and release planning

11:30

10 + 5 min

Bluesquare

Re-architecturing: activity report

11:45

10 + 5 min

SolDevelo

HL7 FHIR mapping & openMRS integration

12:00

10 + 5 min

Possbile Health

BAHMNI Integration

12:15

10 + 5 min

HISP India

DHIS2 Integration

12:30

10 + 5 min

Special guest: Jembi

Progress of OpenHIM

Minutes

SwissTPH

  • Support for Rwandan Company for setting up a local demo instance

  • French translation correction

  • code integration from TZ

  • Tests & bug fixing

  • Documentation

  • Release April 2019

  • Docker package for MS IMIS

  • Next:

    • Issue tracking process

    • Finish April release

    • Involve Exact & integrate repositories

    • formal sector RFC budgeting

    • AEHIN support (Tender 2)

    • Docker image MS IMIS & newly developed modules

Time budget remaining: 183 days of 240 =>  76.27%

Work load remaining:

BlueSquare

Iteration 1:

  • security on backend APIs (FHIR API being the first one)

  • bridge to claim bulk registration stored procedure to allow claim registration from FHIR API.

  • setup a continuous build tool (travis-ci) an a code quality static analysis tool (codeclimat)

Iteration 3:

Time budget remaining:

  • Iteration 1: over 04/2019 - remains 11 m/d on 60 m/d

  • Iteration 2: target 05/2019 - remains 20 m/d on 20 m/d

  • Iteration 3: target 09/2019 - remains 88 m/d on 90 m/d

  • Iteration 4: target 11/2019 remains 60 m/d on 60 m/d

Workload remaining:

  • Iteration 1: ? (bug fixes, adaptations, documentation)

  • Iteration 2: 20 m/d on 20 m/d

  • Iteration 3: 88 m/d on 90 m/d

  • Iteration 4: 60 m/d on 60 m/d

SolDevelo

  • HL7 FHIR mapping - in commenting phase

  • OpenMRS development

  • Issues:

    • needs to provide more wiki-transparancy

    • lack of communication on FHIR mappings (feedback)

Time budget remaining: 75% (130MD / 175MD)

Workload remaining:

  • finish FHIR mapping

  • Start FHIR module implementation on the basis of BlueSquare developments

Possible Health

  • Sprint planning in Jira

  • Roadmaps Epics

  • Sprint 1 report

  • Workflows: insurance integration,

  • Development: integration modules on BAHMNI side in PH Github

  • Issues:

    • DEV/QA integration platform needed,

    • new BAHMNI release,

    • communication on dependencies

  • Next

Time budget remaining: 85%

Workload remaining:

HISP India

  • Indicator definitions

    • Benificiary management finished

    • mapped to FHIR ressources

  • set up local openIMIS environment

  • Next:

    • finalize claims indicators

    • scetch data extracton models

    • draft meta data package in DHIS2 (for rollout to existing DHIS2 implementations)

  • FHIR dummy module to test openIMIS FHIR API

Time budget remaining: 82%

Workload remaining:

Jembi

Presentation link: openIMIS - Integration into the OpenHIE Landscape



Did you encounter a problem or do you have a suggestion?

Please contact our Service Desk



This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License. https://creativecommons.org/licenses/by-sa/4.0/