Gumzo ya Mwezi

The monthly chat (kiswaheli: gumzo ya mwezi) will help the devloper teams to show-case their achievements to the developers committee and to interested members of the implementers committee. The gumzo is oriented at Scrum review sessions: let's celebrate the achievements of the past month!

Co-ordinates

Date: 06.05.2019

Time: 11:00 am (GMT) (Still a bit confused about daylight savings, but I suppose this is the best compromise for all)

Room: https://meet.jit.si/openIMISDevelopers - kindly indicate your name and organisation (jitsi claims to support Chrome, Chromium and Firefox browsers only.  However - screen sharing caused problems on Firefox recently. You might also want to try the jitsi app)

Participants: (kindly only add yourself, not others)

Schedule

After our testrun last month within the developers committee and the co-ordination desk only, we now open it up to the implementers committee as well. Each session is 10 minutes presentation plus 5 minutes Q&A - please have your bio breaks before the event (wink)

Please prepare your presentations with an eye on:

  • what did we achieve last month
  • where are problems
  • where do we want to go next month
  • rough estimation on the remaining time budget and workload
When (GMT)DurationWhoTopic
11:0010 + 5 minWelcome note, overview & current topics
11:1510 + 5 minSwissTPH3rd Level support and release planning
11:3010 + 5 minBluesquareRe-architecturing: activity report
11:4510 + 5 minSolDeveloHL7 FHIR mapping & openMRS integration
12:0010 + 5 minPossbile HealthBAHMNI Integration
12:1510 + 5 minHISP IndiaDHIS2 Integration
12:3010 + 5 minSpecial guest: JembiProgress of OpenHIM

Minutes

SwissTPH

  • Support for Rwandan Company for setting up a local demo instance
  • French translation correction
  • code integration from TZ
  • Tests & bug fixing
  • Documentation
  • Release April 2019
  • Docker package for MS IMIS
  • Next:
    • Issue tracking process
    • Finish April release
    • Involve Exact & integrate repositories
    • formal sector RFC budgeting
    • AEHIN support (Tender 2)
    • Docker image MS IMIS & newly developed modules

Time budget remaining: 183 days of 240 =>  76.27%

Work load remaining:

BlueSquare

Iteration 1:

  • security on backend APIs (FHIR API being the first one)
  • bridge to claim bulk registration stored procedure to allow claim registration from FHIR API.
  • setup a continuous build tool (travis-ci) an a code quality static analysis tool (codeclimat)

Iteration 3:

Time budget remaining:

  • Iteration 1: over 04/2019 - remains 11 m/d on 60 m/d
  • Iteration 2: target 05/2019 - remains 20 m/d on 20 m/d
  • Iteration 3: target 09/2019 - remains 88 m/d on 90 m/d
  • Iteration 4: target 11/2019 remains 60 m/d on 60 m/d

Workload remaining:

  • Iteration 1: ? (bug fixes, adaptations, documentation)
  • Iteration 2: 20 m/d on 20 m/d
  • Iteration 3: 88 m/d on 90 m/d
  • Iteration 4: 60 m/d on 60 m/d

SolDevelo

  • HL7 FHIR mapping - in commenting phase
  • OpenMRS development
  • Issues:
    • needs to provide more wiki-transparancy
    • lack of communication on FHIR mappings (feedback)

Time budget remaining: 75% (130MD / 175MD)

Workload remaining:

  • finish FHIR mapping
  • Start FHIR module implementation on the basis of BlueSquare developments

Possible Health

  • Sprint planning in Jira
  • Roadmaps Epics
  • Sprint 1 report
  • Workflows: insurance integration,
  • Development: integration modules on BAHMNI side in PH Github
  • Issues:
    • DEV/QA integration platform needed,
    • new BAHMNI release,
    • communication on dependencies
  • Next

Time budget remaining: 85%

Workload remaining:

HISP India

  • Indicator definitions
    • Benificiary management finished
    • mapped to FHIR ressources
  • set up local openIMIS environment
  • Next:
    • finalize claims indicators
    • scetch data extracton models
    • draft meta data package in DHIS2 (for rollout to existing DHIS2 implementations)
  • FHIR dummy module to test openIMIS FHIR API

Time budget remaining: 82%

Workload remaining:

Jembi

Presentation link: openIMIS - Integration into the OpenHIE Landscape