Participants: (kindly only add yourself, not others):
- Uwe Wahser
- Xavier Gillmann
- Dragos Dobre
- Patrick Delcroix
- Alicia Spengler
Schedule
The call is specifically addressed to the Developers Committee and the Implementers Committee. Each session consists of 10 minutes presentation plus 5 minutes Q&A - please have your bio breaks before the event
...
When (GMT) | Duration | Who | Topic |
---|---|---|---|
1110:00 | 10 + 5 min | Welcome note, overview & current topics | |
1110:15 | 10 + 5 min | Swiss TPH | 3rd Level support and release planning |
1110:30 | 10 + 5 min | BlueSquare | Re-architecturing |
1110:45 | 10 + 5 min | SolDevelo | HL7 FHIR mapping & openMRS integration |
1211:00 | 10 + 5 min | Possible Health | BAHMNI Integration |
1211:15 | 10 + 5 min | HISP India | DHIS2 Integration |
...
- October Release
- OpenHIE conference + Developers Committee workshop
- Digital Square RFA#2019-16 ("Notice D1")
SwissTPH
Presentation: SwissTPH openIMIS September 2019 report.pptx
Time budget remaining: 122 days (50%)
Discussion:
- Installation manual can be found on the wiki since not many people check ReadTheDocs.
- User manual is still available on ReadTheDocs.
- With localisation, there will be a developer guide.
- SwissTPH: There will be a simple proofreading of translated manual in to french. Bilateral talk with Alicia about this.
- Officially, SwissTPH will start working on the release on 07.10.2019.
BlueSquare
Presentation: openIMIS - Gumzo ya Mwezi - 2019-10-07.pdf
Time budget and workload remaining:
- Iteration 1 (FHIR API): 56/60 m/d;
- Iteration 2 (All proxy frontend)- CLOSED (18.5 / 20 m/d)
- Iteration 3 (Claim module): 86/90 m/d
- Iteration 4 (Module n°2): 0 / 60 m/d
Discussion:
- Patrick has written on the wiki the tests that Bluesquare is doing for the claim module.
- For implementers, verifying mechanisms are needed to check whether case tests that need to be rejected are indeed rejected (relevant for SwissTPH).
- Xavier will create an event to talk about questions related to the run batch and reports.
SolDevelo
Presentation: View file
Time budget remaining:
- 47% (83MD / 175MD)
Workload remaining:
Discussion:
- Schedule short call between Tomas and Uwe.
Possible Health - not available this month
Presentation slides:
Time budget remaining:
...
Presentation:
Time budget remaining: 50%
Workload remaining:
Discussion:
- Harsh will create issue in the issue qeue related to the timestap.
Other Topics
Harsh: Both insuree and claims will also be on DHIS2
Schedule a call between Harsh and Kamil to talk about policies?
Xavier: An own module can be added where you can have endpoints.