Table of Contents |
---|
Gumzo ya Mwezi
The monthly chat (kiswaheli: gumzo ya mwezi) will help the developer teams to show-case their achievements to the developers committee and to interested members of the implementers committee. The gumzo is oriented at Scrum review sessions: let's celebrate the achievements of the past month!
Co-ordinates
Date: 02.12.2019
Time: 11:00 am (GMT)
Room: https://meet.jit.si/openIMISDevelopers - kindly indicate your name and organisation (jitsi claims to support Chrome, Chromium and Firefox browsers only. However - screen sharing caused problems on Firefox recently. You might also want to try the jitsi app)
Participants: (kindly only add yourself, not others):
...
Please prepare your presentations with an eye on:
what did we achieve last month
where are problems
where do we want to go next month
rough estimation on the remaining time budget and workload
When (GMT) | Duration | Who | Topic |
---|---|---|---|
11:00 | 10 + 5 min | Welcome note, overview & current topics | |
11:15 | 10 + 5 min | 3rd Level support and release planning | |
11:30 | 10 + 5 min | Re-architecturing | |
11:45 | 10 + 5 min | HL7 FHIR mapping & openMRS integration | |
12:00 | 10 + 5 min | BAHMNI Integration | |
12:15 | 10 + 5 min | DHIS2 Integration |
Minutes
GIZ
Welcome
Recall OpenHIE (Developers Workshop) & Helina
Preview GDHF
Overview of new projects from Digital Square RFA#2019-16 ("Notice D1")
SwissTPH
Presentation: SwissTPH openIMIS November 2019.pptx
...
Time budget and workload remaining:
Iteration 1 (FHIR API): 56.5 / 60 m/d
Iteration 2 (All proxy frontend)- CLOSED
Iteration 3 (Claim module): 120.5 / 90 m/d (and still 10 m/d to go for
the Batchthe Batch Processing stored proc)
Iteration 4 (Locations): 6.5 / 60 m/d (and still 13 m/d to go to implement the HFs part)
Discussion:
Bulk import/export from csv, xml,... not part of the scope at the moment.
Maybe the feature to add in the 15 spared m/d (to be decided in Janurary) - or use FHIR
SolDevelo
Presentation:
View file | ||
---|---|---|
|
...
Time budget & workload remaining:
25% (70MD / 285MD)
Discussion:
Possible Health
...