Gumzo ya Mwezi

The monthly chat (kiswaheli: gumzo ya mwezi) will help the developer teams to show-case their achievements to the developers committee and to interested members of the implementers committee. The gumzo is oriented at Scrum review sessions: let's celebrate the achievements of the past month!

Co-ordinates

Date: 01.07.2019

Time: 11:00 am (GMT) (Still a bit confused about daylight savings, but I suppose this is the best compromise for all)

Room: https://meet.jit.si/openIMISDevelopers - kindly indicate your name and organisation (jitsi claims to support Chrome, Chromium and Firefox browsers only.  However - screen sharing caused problems on Firefox recently. You might also want to try the jitsi app)

Participants: (kindly only add yourself, not others)

Schedule

The call is specifically addressed to the Developers Committee and the Implementers Committee. Each session consists of 10 minutes presentation plus 5 minutes Q&A - please have your bio breaks before the event (wink)

Please prepare your presentations with an eye on:

  • what did we achieve last month
  • where are problems
  • where do we want to go next month
  • rough estimation on the remaining time budget and workload
When (GMT)DurationWhoTopic
11:0010 + 5 minWelcome note, overview & current topics
11:1510 + 5 minSwissTPH3rd Level support and release planning
11:3010 + 5 minBluesquareRe-architecturing
11:4510 + 5 minSolDeveloHL7 FHIR mapping & openMRS integration
12:0010 + 5 minPossbile HealthBAHMNI Integration
12:1510 + 5 minHISP IndiaDHIS2 Integration

Minutes

SwissTPH

Presentation: SwissTPH openIMIS June report.pptx

Time budget remaining: 62% 

Work load remaining: 149 MD / 240 MD

BlueSquare

Presentation:

Time budget and workload remaining:

Iteration 1 (FHIR API):

Iteration 2 (All proxy frontend):

Iteration 3 (Claim module):

Iteration 4 (Module n°2):

SolDevelo

Presentation: https://docs.google.com/presentation/d/1VwvklcY00oudD_6Vpt_xUd5-Ij123h74Y8IfKFYF7Ug/edit?usp=sharing

Time budget remaining: 59 % (102,5MD / 175MD)

Workload remaining:

Possible Health

Presentation slides :https://docs.google.com/presentation/d/1EMSE4DFBGI0ciVttqOe55WXw8505XswahVU2DwgnpJA/edit#slide=id.p1

Time budget remaining:~57%

Workload remaining:

HISP India (not available this month)

Presentation: 

Time budget remaining:

Workload remaining: