Gumzo ya Mwezi

The monthly chat (kiswaheli: gumzo ya mwezi) will help the devloper teams to show-case their achievements to the developers committee and to interested members of the implementers committee. The gumzo is oriented at Scrum review sessions: let's celebrate the achievements of the past month!

Co-ordinates

Date: 06.05.2019

Time: 11:00 am (GMT) (Still a bit confused about daylight savings, but I suppose this is the best compromise for all)

Room: https://meet.jit.si/openIMISDevelopers - kindly indicate your name and organisation (jitsi claims to support Chrome, Chromium and Firefox browsers only.  However - screen sharing caused problems on Firefox recently. You might also want to try the jitsi app)

Participants: (kindly only add yourself, not others)

Schedule

After our testrun last month within the developers committee and the co-ordination desk only, we now open it up to the implementers committee as well. Each session is 10 minutes presentation plus 5 minutes Q&A - please have your bio breaks before the event (wink)

Please prepare your presentations with an eye on:

  • what did we achive last month
  • where are problems
  • where do we want to go next month
  • rough estimation on the remaining time budget and workload
When (GMT)DurationWhoTopic
11:0010 + 5 minWelcome note, overview & current topics
11:1510 + 5 minSwissTPH3rd Level support and release planning
11:3010 + 5 minBluesquareRe-architecturing: activity report
11:4510 + 5 minSolDeveloHL7 FHIR mapping & openMRS integration
12:0010 + 5 minPossbile HealthBAHMNI Integration
12:1510 + 5 minHISP IndiaDHIS2 Integration
12:3010 + 5 minSpecial guest: JembiProgress of OpenHIM

Minutes

SwissTPH

  • Support for Rwandan Company for setting up a local demo instance
  • French translation correction
  • code integration from TZ
  • Tests & bug fixing
  • Documentation

Time budget remaining:

Work load remaining:

BlueSquare

  • security on backend APIs (FHIR API being the first one)

Time budget remaining:

  • Iteration 1: over 04/2019 - remains 11 m/d on 60 m/d
  • Iteration 2: target 05/2019 - remains 20 m/d on 20 m/d
  • Iteration 3: target 09/2019 - remains 88 m/d on 90 m/d
  • Iteration 4: target 11/2019 remains 60 m/d on 60 m/d

Workload remaining:

  • Iteration 1: ? (bug fixes, adaptations, documentation)
  • Iteration 2: 20 m/d on 20 m/d
  • Iteration 3: 88 m/d on 90 m/d
  • Iteration 4: 60 m/d on 60 m/d

SolDevelo

Time budget remaining: 75% (130MD / 175MD)

Workload remaining:

Possible Health

Time budget remaining:

Workload remaining:

HISP India

Time budget remaining:

Workload remaining:

Jembi

Presentation link: openIMIS - Integration into the OpenHIE Landscape