BlueSquare - Notice D1: Beneficiaries, Policies, Contributions

...

  • Iteration 1: Dev readiness - 24.5 m/d (on 20) : 4.5 overrun (-> iteration 5 contingency) - closed

  • Iteration 2: Insurees & Families - 29 50 m/d (on 50) - continued module implementation - deadline 30/09 closed

  • Iteration 3: Policies - 21 m/d (50 m/d) deadline 30/11

  • Iteration 4: Contributions - (50 m/d) - deadline 31/01

  • Iteration 5: Closure - (20 m/d -> 15.5 m/d) - deadline 28/02

...

Remaining deliverables:

Discussion:

Healthix - Notice D.1: Formal Sector API

...