what did we achieve last month
where are problems
where do we want to go next month
rough estimation on the remaining time budget and workload
When (UCT) | Duration | Who | Topic |
---|---|---|---|
11:00 (UCT) | 10 + 5 min | Welcome note, overview & current topics | |
11:15 (UCT) | 10 + 5 min | Project: 2020.T1 Maintenance: 3rd Level support and release planning | |
11:30 (UCT) | 10 + 5 min | ||
11:45 (UCT) | 10 + 5 min | Project: D1 Migration (Beneficiaries, Product, Enrollment, Payment) | |
12:00 (UCT) | 10 + 5 min | ||
12:15 (UCT) | 10 + 5 min | ||
12:30 (UCT) | 10 + 5 min | ||
12:45 (UCT) | 10 + 5 min | ||
13:00 (UCT) | 10 + 5 min | GIZ Nepal | New Features from Nepal |
Minutes
GIZ
Community Workshop coming up: openIMIS Community Meeting (March 2021)
...
updated documentation of the process: openIMIS AI-based Claim Adjudication (in development)
BlueSquare - Notice D1: Beneficiaries, Policies, Contributions
...
Remaining deliverables:
Discussion:
Formal Sector Modules (in development)
Healthix - Notice D.1: Formal Sector API
...
Please fill the evaluation form after every call (see link in top ). The results will be updated here, if there is sufficient feedback:
...
Legend
Expand | ||
---|---|---|
| ||
Overall mood (status): GFL: General feeling about the meeting [very disappointed … very glad] Event parameters of the meeting (XYZ needs to be ...): DET: Degree of detail [more condensed … more detailed] |