The monthly chat (kiswaheli: gumzo ya mwezi) will help the developer teams to show-case their achievements to the developers committee and to interested members of the implementers committee. The gumzo is oriented at Scrum review sessions: let's celebrate the achievements of the past month!
Date: 01.03.2021
Time: 11:00 am (UCT)
Room: https://meet.jit.si/openIMISDevelopers - kindly indicate your name and organisation (jitsi claims to support Chrome, Chromium & MS Edge and Firefox browsers only. You might also want to try the jitsi app)
Participants: (kindly only add yourself, not others):
The call is specifically addressed to the Developers Committee and the Implementers Committee. Each session consists of 10 minutes presentation plus 5 minutes Q&A - please have your bio breaks before the event
Please prepare your presentations with an eye on:
what did we achieve last month
where are problems
where do we want to go next month
rough estimation on the remaining time budget and workload
When (UCT) | Duration | Who | Topic |
---|---|---|---|
11:00 (UCT) | 10 + 5 min | Welcome note, overview & current topics | |
11:15 (UCT) | 10 + 5 min | Project: 2020.T1 Maintenance: 3rd Level support and release planning | |
11:30 (UCT) | 10 + 5 min | ||
11:45 (UCT) | 10 + 5 min | Project: D1 Migration (Beneficiaries, Product, Enrollment, Payment) | |
12:00 (UCT) | 10 + 5 min | ||
12:15 (UCT) | 10 + 5 min | ||
12:30 (UCT) | 10 + 5 min | ||
12:45 (UCT) | 10 + 5 min | ||
13:00 (UCT) | 10 + 5 min | GIZ Nepal | New Features from Nepal |
Community Workshop coming up: openIMIS Community Meeting (March 2021)
Presentation:
Time budget remaining and workload remaining: 87% remaining
Discussion:
issue on submitting more than 500 insuree, issue on OSD will be created
Presentation:
Time budget remaining and workload remaining:
Discussion:
updated documentation of the process: openIMIS AI-based Claim Adjudication
Presentation:
Time budget and workload remaining:
Iteration 1: Dev readiness - 24.5 m/d (on 20) : 4.5 overrun (-> iteration 5 contingency) - closed
Iteration 2: Insurees & Families - 29 m/d (on 50) - continued module implementation - deadline 30/09 - closed
Iteration 3: Policies - (50 m/d) deadline 30/11 - closed
Iteration 4: Contributions - (50 m/d) - deadline 31/01
Iteration 5: Closure - (20 m/d -> 15.5 m/d) - deadline 28/02
Discussion:
Presentation:
Time budget and workload remaining:
Discussion:
Presentation:
Status / Remaining budget:
on track
Remaining deliverables:
Discussion:
Presentation: not available
Time budget remaining and workload remaining:
Discussion:
docker was delivered
Presentation: not available
Time budget remaining and workload remaining:
Discussion:
Final Demo at SSF tomorrow
go live coming up soon
Mobile reporting based on the DHIS2 dashboard?
Please fill the evaluation form after every call (see link in top ). The results will be updated here, if there is sufficient feedback:
Legend
Overall mood (status): GFL: General feeling about the meeting [very disappointed … very glad] Event parameters of the meeting (XYZ needs to be ...): DET: Degree of detail [more condensed … more detailed] |