Gumzo ya Mwezi
The monthly chat (kiswaheli: gumzo ya mwezi) will help the developer teams to show-case their achievements to the developers committee and to interested members of the implementers committee. The gumzo is oriented at Scrum review sessions: let's celebrate the achievements of the past month!
...
Participants: (kindly only add yourself, not others):
Schedule
The call is specifically addressed to the Developers Committee and the Implementers Committee. Each session consists of 10 minutes presentation plus 5 minutes Q&A - please have your bio breaks before the event
...
When (GMT) | Duration | Who | Topic |
---|---|---|---|
11:00 (GMT) | 10 + 5 min | Welcome note, overview & current topics | |
11:15 (GMT) | 10 + 5 min | 3rd Level support and release planning | |
11:30 (GMT) | 10 + 5 min | Re-architecturing | |
11:45 (GMT) | 10 + 5 min | DHIS2 Integration | |
12:00 (GMT) | 10 + 5 min | DB Migration MSSQL → PostgreSQL | |
12:15 (GMT) | 10 + 5 min | Notice D.1: AI claims adjudication | |
12:30 (GMT) | 10 + 5 min | Notice D.1: Beneficiaries, Policies, Contributions | |
12:45 (GMT) | 10 + 5 min | 2M | Guest presentation: Proof of concept: openIMIS in cash transfer |
Minutes
GIZ
...
Welcome
New Notice D.1 projects
New student projects
SwissTPH (3rd Level support and release planning)
Presentation:
View file | ||
---|---|---|
|
Time budget remaining and workload remaining: 15 days left
Discussion:
need to set up a better way of documenting release notes per module
BlueSquare (Re-architecturing)
Presentation:
View file | ||
---|---|---|
|
Time budget and workload remaining:
Iteration 1 (FHIR API) - 56,5 / 60 m/d CLOSED
Iteration 2 (All proxy frontend)- 18,5 / 20 m/d CLOSED
Iteration 3 (Claim module) - 144 m/d on 90 m/d reopened and CLOSED again
Iteration 4 (Locations) - 16,5 m/d on 20 m/d reopened and CLOSED again
Closing & extensions: - 11,5 m/d on 4,5 m/d, CLOSED
Discussion:
...
All closed, roadmap for next phase
Discussion:
HISP India (DHIS2 Dashboards)
Presentation:
View file | ||
---|---|---|
|
Time budget & workload remaining: 70% spent
Discussion:
Demo installation: DHIS2 test instance for Indicator Dashboards
Installation documentation will follow this month
current version of health facility synchronisation is fully dependant on openIMIS
Michel (DB-Migration)
Presentation:
View file | ||
---|---|---|
|
Time budget & workload remaining: available until end of June
Discussion:
SwissTPH (AI supported claims adjudication)
Presentation:
Time budget & workload remaining:
Discussion:
Bluesquare (Beneficiary migration)
Presentation:
Time budget & workload remaining:
Discussion:
Other Topics
iperson-family migration might require slight DB-modifications beyond simple migration (e.g. enable person without family, foreign key issue)
fine tuning of roadmap needs to be done together with the other teams as soon as possible