Schedule

After our testrun last month within the developers committee and the co-ordination desk only, we now open it up to the implementers committee as well. Each session is 10 minutes presentation plus 5 minutes Q&A - please have your bio breaks before the event (wink)

...

When (GMT)DurationWhoTopic
11:0010 + 5 minWelcome note, overview & current topics
11:1510 + 5 minSwissTPH3rd Level support and release planning
11:3010 + 5 minBluesquareRe-architecturing: activity report
11:4510 + 5 minSolDeveloHL7 FHIR mapping & openMRS integration
12:0010 + 5 minPossbile HealthBAHMNI Integration
12:1510 + 5 minHISP IndiaDHIS2 Integration
12:3010 + 5 minSpecial guest: JembiProgress of OpenHIM

Minutes

SwissTPH

  • Support for Rwandan Company for setting up a local demo instance
  • French translation correction
  • code integration from TZ
  • Tests & bug fixing
  • Documentation

Time budget remaining:

Work load remaining:

BlueSquare

  • security on backend APIs (FHIR API being the first one)

Time budget remaining:

  • Iteration 1: over 04/2019 - remains 11 m/d on 60 m/d
  • Iteration 2: target 05/2019 - remains 20 m/d on 20 m/d
  • Iteration 3: target 09/2019 - remains 88 m/d on 90 m/d
  • Iteration 4: target 11/2019 remains 60 m/d on 60 m/d

...