When (GMT)DurationWhoTopic
11:0010 + 5 minWelcome note, overview & current topics
11:1510 + 5 minSwiss TPH3rd Level support and release planning
11:3010 + 5 minBlueSquare

Re-architecturing

11:4510 + 5 minSolDeveloHL7 FHIR mapping & openMRS integration
12:0010 + 5 minHISP IndiaDHIS2 Integration
12:1510 + 5 minPossible HealthBAHMNI Integration

Minutes

GIZ

  • WelcomeWelcome                                                                                                                                                                              

SwissTPH

Presentation:

Time budget remaining and workload remaining:

Discussion: 


BlueSquare

Presentation: openIMIS - Gumzo ya Mwezi - 2020-02-03.pdf

Time budget and workload remaining:

  • Iteration 1 (FHIR API):56,5 / 60 m/d CLOSED
  • Iteration 2 (All proxy frontend)- 18,5 / 20 m/d CLOSED
  • Iteration 3 (Claim module): 121,5 / 90 m/d (still ~ 15 m/d to go)
  • Iteration 4 (Locations): 15,5 / 60 m/d (still ~5 m/d to go)
  • Closing & extensions: 3,5 / 10 m/d