The Release Cycle

openIMIS is released twice a year. The plan is to have a new release out in April and October every year. For each release cycle there is a fixed sequence of phases that the software has to pass:

Phase

Activities

April

October

Platform

Phase

Activities

April

October

Platform

Freeze

Feature freeze

end of February

end of August

Alpha

IT Testing

two weeks

Beta

User acceptance testing & bugfixing

one month

RC

Final release candidate

two weeks

GA

General availability - release date

by end of April

 

by end of October

 

The Release Roadmap

These are the timelines of the openIMIS releases: