The monthly chat (kiswaheli: gumzo ya mwezi) will help the devloper teams to show-case their achievements to the developers committee and to interested members of the implementers committee. The gumzo is oriented at Scrum review sessions: let's celebrate the achievements of the past month!
Date: 03.06.2019
Time: 11:00 am (GMT) (Still a bit confused about daylight savings, but I suppose this is the best compromise for all)
Room: https://meet.jit.si/openIMISDevelopers - kindly indicate your name and organisation (jitsi claims to support Chrome, Chromium and Firefox browsers only. However - screen sharing caused problems on Firefox recently. You might also want to try the jitsi app)
Participants: (kindly only add yourself, not others)
The call is specifically addressed to the Developers Committee and the Implementers Committeel. Each session is 10 minutes presentation plus 5 minutes Q&A - please have your bio breaks before the event
Please prepare your presentations with an eye on:
When (GMT) | Duration | Who | Topic |
---|---|---|---|
11:00 | 10 + 5 min | Welcome note, overview & current topics | |
11:15 | 10 + 5 min | SwissTPH | 3rd Level support and release planning |
11:30 | 10 + 5 min | Bluesquare | Re-architecturing activity report |
11:45 | 10 + 5 min | SolDevelo | HL7 FHIR mapping & openMRS integration |
12:00 | 10 + 5 min | Possbile Health | BAHMNI Integration |
12:15 | 10 + 5 min | HISP India | DHIS2 Integration |
Presentation: SwissTPH openIMIS May report.pptx
Time budget remaining:171 - 71%
Work load remaining:
Presentation: openIMIS - Gumzo ya Mwezi - 2019-06-03 - Bluesquare.pdf
Time budget and workload remaining:
Iteration 1 (FHIR API): overdue (04/2019) - budget remaining: 7 m/d on 60 m/d
Iteration 2 (All proxy frontend): overdue (05/2019) - budget remaining: 10 m/d on 20 m/d
Iteration 3 (Claim module): in progress (deadline 09/2019) - budget remaining: 87.5 m/d on 90 m/d
Iteration 4 (Module n°2): not started (deadline 11/2019) budget remaining: 60 m/d on 60 m/d
Discussion:
Time budget remaining: 67% (117MD / 175MD)
Workload remaining:
Showcase FHIR Patient endpoint- https://drive.google.com/open?id=1adh4g4FnhDRKN5rKyHUoj6AVsaGO7nuL
Presentation - https://drive.google.com/open?id=1Ia_qyNeT5LkSF2mZlwcjM0zcHSVmFFbhbKF8hFkNAg8
Discussion:
Presentation slides : https://docs.google.com/presentation/d/13t8Kd3JdRR_TzDJBqSlzMvl6mR6G1r-FBdBEF3ENxs4/edit#slide=id.p2
Time budget remaining: ~70%
Workload remaining:
Discussion:
Time budget remaining: