When (GMT) | Duration | Who | Topic |
---|---|---|---|
11:00 | 10 + 5 min | Welcome note, overview & current topics | |
11:15 | 10 + 5 min | SwissTPH | 3rd Level support and release planning |
11:30 | 10 + 5 min | Bluesquare | Re-architecturing activity report |
11:45 | 10 + 5 min | SolDevelo | HL7 FHIR mapping & openMRS integration |
12:00 | 10 + 5 min | Possbile Health | BAHMNI Integration |
12:15 | 10 + 5 min | HISP India | DHIS2 Integration |
Minutes
SwissTPH
Presentation: SwissTPH openIMIS May report.pptx
Time budget remaining:171 - 71%
Work load remaining:
BlueSquare
Presentation: openIMIS - Gumzo ya Mwezi - 2019-06-03 - Bluesquare.pdf
Time budget and workload remaining:
...
Iteration 4 (Module n°2): not started (deadline 11/2019) budget remaining: 60 m/d on 60 m/d
Discussion:
- Discussion with implementers implementer on content (Claim module scope) and user interface (https://material.io/design/components/data-tables.html#)
- Claims module needs discussion on user information design (options: less details in tables https://material.io/design/components/data-tables.html#)
- menu structure of new frontend front-end will be oriented at module structure
- https://openimis.nepalehr.org
SolDevelo
Time budget remaining: 67% (117MD / 175MD)
Workload remaining:
Discussion:
- Permissions need to be added for access, currently only login required.
Possible Health
Presentation slides : https://docs.google.com/presentation/d/13t8Kd3JdRR_TzDJBqSlzMvl6mR6G1r-FBdBEF3ENxs4/edit#slide=id.p2
Time budget remaining: ~70%
Workload remaining:
Discussion:
- Bahmi will have capability to receive claims from openIMIS with release 0.92 - coming up soon.
HISP India (not available today)
Time budget remaining:
Workload remaining:
...