Schedule
The call is specifically addressed to the Developers Committee and the Implementers Committee. Each session consists of 10 minutes presentation plus 5 minutes Q&A - please have your bio breaks before the event
...
- Welcome
SwissTPH
Presentation: SwissTPH openIMIS February 2020.pptx
Time budget remaining and workload remaining: 46d (19.17%)
Discussion:
BlueSquare
Presentation: openIMIS - Gumzo ya Mwezi - 2020-03-02.pdf
Time budget and workload remaining:
- Iteration 1 (FHIR API) :- 56,5 / 60 m/d CLOSED
- Iteration 2 (All proxy frontend)- 18,5 / 20 m/d CLOSED
- Iteration 3 (Claim module) : - 132 m/d on 90 m/d CLOSED
- Iteration 4 (Locations) :- 15,5 m/d on 20 m/d CLOSED
- Closing & extensions: - 6,5 m/d on 18,5 m/d
Discussion:
- how to integrate locally added features into the master version → take discussion to Implementers Committee
HISP India
Presentation:
Time budget & workload remaining:
...