  • openIMIS

    • core modules (STPH/SolDevelo)

    • FHIR APIs (STPH/SolDevelo) -

      • definitions: End of this week

      • development: end of next week

    • Payment Switch APIs & module (2M-Corp)

    • MojaLoop customisations/configuration

      • development (2M-Corp)

      • packaging of customisations (2M-Corp)

      • packaging/availing of core software

    • MIFOS customisations/configuration (Healthix)

      • development (Healthix)

        • how can openIMIS accounts be translated to MIFOS? What needs to be done in MIFOS without copying existing openIMIS functionality?

      • packaging of customisations (Healthix)

        • how can the developments packaged and pushed in to a bare MIFOS installation?

      • packaging/availing of core software (link to docker version was shared) - (STPH T1)

      • demo:

        • need to receive demo data

    • OpenHIM customisation/ configuration

      • aligning openIMIS (FHIR) to MIFOS (Financial Standards?) - mapping matches to 80% what about the rest? (Healthix)

      • development of the mediators (MTCC)

      • packaging of the mediators (MTCC)

      • packaging/availing the core software (STPH T1)

        • docker compose needs to include special port configurations for nginx (MTCC <> STPH)

    • Sandbox

      • install openIMIS (STPH)

        • solution on release: BE done, FE end of December

        • QA/showcase: STPH in JanuaryFebruary

        • Documentation: design documents in the wiki, overview page

      • install MojaLoop ( ? STPH / 2MCorp )

        • Developments: second first week Januaryof February

        • QA/showcase: 2M Corp in end of February

        • Documentation: in February

      • install MIFOS (STPH)

        • solution on release: done

        • QA/showcase: Healthix - JanuaryFebruary

        • Documentation: documentation on project page (verify)

      • install openHIM (STPH)

        • solution on release: first week of JanuaryFebruary

        • QA/showcase: MTCC - Januaryfirst week of February

        • Documentation: mapping document on the wiki, ongoing

      • First test-run: second week of February