Schedule

The call is specifically addressed to the Developers Committee and the Implementers Committee. Each session consists of 10 minutes presentation plus 5 minutes Q&A - please have your bio breaks before the event (wink)

...

3rd Level support and release planning

Presentation: 

View file
name2020-07-SwissTPH-Maintenance and Support.pptx

Time budget remaining and workload remaining: 76 days (24.84%)

Discussion:

Notice D.1: AI

Presentation: 

View file
name2020-07-SwissTPH-openIMIS-AI.pptx

Time budget remaining and workload remaining: on track

Discussion:

  • how to validate the results of the AI algorithms?

Notice D.1: Formal Sector

Presentation: 

View file
nameSwissTPH openIMIS FS July 2020.pptx

Time budget remaining and workload remaining:

Discussion:

  • No question asked

Major points:

  • Contract not signed yet

BlueSquare (Notice D1: Beneficiaries, Policies, Contributions)

Presentation:

View file
nameopenIMIS - Gumzo ya Mwezi - 2020-08-03.pdf

Time budget and workload remaining:

  • Iteration 1: Dev readiness - 24.5 m/d (on 20) : 4.5 overrun (-> iteration 5 contingency) - closed

  • Iteration 2: Insurees & Families - 2 29 m/d (on 50) - analysis (screen mocks done) continued module implementation - deadline 30/09

  • Iteration 3: Policies - (50 m/d) deadline 30/11

  • Iteration 4: Contributions - (50 m/d) - deadline 31/01

  • Iteration 5: Closure - (20 m/d -> 15.5 m/d) - deadline 28/02

...

Faris (FHIR4)

Presentation: 

View file
nameFHIR R4 Presentation - final.pptx

Time budget & workload remaining: report remaining,

...