Participants: (kindly only add yourself, not others):
Schedule
The call is specifically addressed to the Developers Committee and the Implementers Committee. Each session consists of 10 minutes presentation plus 5 minutes Q&A - please have your bio breaks before the event
...
what did we achieve last month
where are problems
where do we want to go next month
rough estimation on the remaining time budget and workload
When (UCT) | Duration | Who | Topic |
---|---|---|---|
11:00 (UCT) | 10 + 5 min | Welcome note, overview & current topics | |
11:15 (UCT) | 10 + 5 min | 3rd Level support and release planning | |
11:30 (UCT) | 10 + 5 min | Notice D.1: AI | |
11:45 (UCT) | 10 + 5 min | Notice D.1: Beneficiaries, Policies, Contributions | |
12:00 (UCT) | 10 + 5 min | Tender 3: Modular Migration | |
12:15 (UCT) | 10 + 5 min | Notice D.1: Formal Sector | |
12:30 (UCT) | 10 + 5 min | Notice D.1: Formal Sector APIs | |
12:45 (UCT) | 10 + 5 min | Accident Insurance Nepal (EII) | |
13:00 (UCT) | 10 + 5 min |
|
Minutes
GIZ
Implementers committee launches monthly review meetings similar to our Gumzo called Bhela (भेला) (Nepali for Gathering)
SwissTPH - 3rd Level support and release planning
Presentation:
View file | ||
---|---|---|
|
Time budget remaining and workload remaining: 91% 89% remaining
Discussion:
new servers are being set up : Server Landscape
SwissTPH - Notice D.1: AI
Presentation:
View file | ||
---|---|---|
|
Time budget remaining and workload remaining:
...
updated documentation of the process: openIMIS AI-based Claim Adjudication (in development)
BlueSquare - Notice D1: Beneficiaries, Policies, Contributions
...
Iteration 1: Dev readiness - 24.5 m/d (on 20) : 4.5 overrun (-> iteration 5 contingency) - closed
Iteration 2: Insurees & Families - 29 m/d (on 50) - continued module implementation - deadline 30/09 - closed
Iteration 3: Policies - (50 m/d) deadline 30/11 - closed
Iteration 4: Contributions - (50 m/d) - deadline 31/01
Iteration 5: Closure - (20 m/d -> 15.5 m/d) - deadline 28/02
Discussion:
BlueSquare -
...
T3: Modular Transformation
Presentation:
Time budget and workload remaining:
Discussion:
Strategy workshop on Thursday
View file | ||
---|---|---|
|
SwissTPH - Notice D.1: Formal Sector
Presentation:
View file | ||
---|---|---|
|
Status / Remaining budget:
on track
Remaining deliverables:
contract
calculation
profile
PH portal
Discussion:
Formal Sector Modules (in development)
https://modular.fs.swisstph-mis.ch/front/contributionPlanBundles
developers demo guis: Admin/admin123
Healthix - Notice D.1: Formal Sector API
...