Overview

Date: 2023-1012-0305

Objective: Reconiliation adjustments and OpenSearch

Participants:

Minutes

  1. OpenSearch update

    1. Proof of concept for the report was created and it’s available under the Dashboard module in the CORE-MIS server

    2. We found the issue with the import (used for reports template for future use by Implementation). We’ve already detected the problem and prepared a fix for that. It should be available on test server today/tomorrow.

    3. iFrame should limit the possibility of making the changes on the dashboards for users. OpenSearch permission (users) can be included in the 2nd phase of the project

  2. My tasks

    1. deleted groups are visible under the drop down - it has to be fixed

    2. issue on the Benefit Plan Update Task → error once checking the details page

...

  1. Draft phases for this project

    1. Stage I - Bug fixes and missing functionalities from initial phase

      1. In relation to the WB feedback, we should spent some time in adjusting the existing modules into the requirements - https://docs.google.com/spreadsheets/d/1sEJ2QBiPEO7MX9EnblBM0Cplq9L6mtOv/edit#gid=417237253

      2. Based on the previous requirements we should define the 2nd phase starting point

      3. Main goal - before new development starts  we need to adjust currently existing modules to the MVP requirements

    2. Stage I a - Previous development analysis

      1. SolDevelo to prepare a detailed demo for each of the delivered modules (ideally based on the WB/GIZ feedback with what is unknown - it will make these demo effective)

      2. Existing modules UML diagrams to visualize the business process - this was missing in the initial phase

    3. Stage II - New development requirements

      1. Gathering the priorities for new development

      2. WB - to prepare the business requirements and diagrams for the visualization

      3. SolDevelo to prepare a new migration plan (to be discussed on a daily basis before the final plan is ready).

        • Note: The plan may be changed during the development but it’s crucial for all involved in the project to be on the same page before development starts

    4. Deliverable - Inception report, Roadmap, Development plan

    5. Stage III Development

      • Strong cooperation - daily meetings (stand ups)

      • Backlog refinements - with WB participation when the tickets are clarified

      • Longer sprints

      • Cooperation in defining Sprint Goal

      • Additional meeting for requirements clarification

Action items

  • Artur Lebiedziński to prepare a example of the ticket monitoring structre in Jira

  • Artur Lebiedziński to create a reccuring meetings and send the invitation

  • malike Andrea define the priorirites within each modules - so the point when we can consider the feature as done

Additional resources

Module Narratives openIMIS-coreMIS