When (GMT)DurationWhoTopic
11:0010 + 5 minWelcome note, overview & current topics
11:1510 + 5 minSwissTPH3rd Level support and release planning
11:3010 + 5 minBluesquareRe-architecturing activity report
11:4510 + 5 minSolDeveloHL7 FHIR mapping & openMRS integration
12:0010 + 5 minPossbile HealthBAHMNI Integration
12:1510 + 5 minHISP IndiaDHIS2 Integration

Minutes

SwissTPH

Presentation: SwissTPH openIMIS May report.pptx

Time budget remaining:171 - 71%

Work load remaining:

BlueSquare

Presentation: openIMIS - Gumzo ya Mwezi - 2019-06-03 - Bluesquare.pdf

Time budget and workload remaining:

...

Iteration 4 (Module n°2): not started (deadline 11/2019) budget remaining: 60 m/d on 60 m/d

Discussion:

SolDevelo

Time budget remaining: 67% (117MD / 175MD)

Workload remaining:

Discussion:

  • Permissions need to be added for access, currently only login required.

Possible Health

Presentation slides : https://docs.google.com/presentation/d/13t8Kd3JdRR_TzDJBqSlzMvl6mR6G1r-FBdBEF3ENxs4/edit#slide=id.p2

Time budget remaining: ~70%

Workload remaining:

Discussion:

  • Bahmi will have capability to receive claims from openIMIS with release 0.92 - coming up soon.

HISP India (not available today)

Time budget remaining:

Workload remaining:

...