The monthly chat (kiswaheli: gumzo ya mwezi) will help the developer teams to show-case their achievements to the developers committee and to interested members of the implementers committee. The gumzo is oriented at Scrum review sessions: let's celebrate the achievements of the past month!

Co-ordinates

View file
name2020-09-SwissTPH-AI Claim Categorisation.pptx

Date: 09.07.2020

Time: 11:00 am (UCT)

Room: https://meet.jit.si/openIMISDevelopers - kindly indicate your name and organisation (jitsi claims to support Chrome, Chromium & MS Edge and Firefox browsers only.  You might also want to try the jitsi app)

Participants: (kindly only add yourself, not others):

Evaluation form: https://docs.google.com/forms/d/e/1FAIpQLSekY3IntsvuYQQbv3YZFYGYDN-9XiotCqOodDBSIv2uyib8fQ/viewform?usp=pp_url&entry.1454293169=Monthly+Gumzo&entry.1968821444=2020-09-07Participants: (kindly only add yourself, not others):

Schedule

The call is specifically addressed to the Developers Committee and the Implementers Committee. Each session consists of 10 minutes presentation plus 5 minutes Q&A - please have your bio breaks before the event (wink)

...

SwissTPH - 3rd Level support and release planning

Presentation: 

View file
name2020-08-SwissTPH-Maintenance and Support.pptx

Time budget remaining and workload remaining: 41 days (13.62%)

Discussion:

  • October release will start - dates to be published later

SwissTPH - Notice D.1: AI

...

Time budget remaining and workload remaining: on track

Discussion:

  • New test data with transformed dates will be sent

View file
name2020-09-SwissTPH-AI Claim Categorisation.pptx

BlueSquare - Notice D1: Beneficiaries, Policies, Contributions

...

Presentation:

Time budget and workload remaining:

  • Iteration 1: Dev readiness - 24.5 m/d (on 20) : 4.5 overrun (-> iteration 5 contingency) - closed

  • Iteration 2: Insurees & Families - 29 m/d (on 50) - continued module implementation - deadline 30/09

  • Iteration 3: Policies - (50 m/d) deadline 30/11

  • Iteration 4: Contributions - (50 m/d) - deadline 31/01

  • Iteration 5: Closure - (20 m/d -> 15.5 m/d) - deadline 28/02

View file
nameBluesquare openIMIS - Gumzo ya Mwezi - 2020-09-07.pptx

Discussion:   

  • testing response has improved a lot

  • developers training coming up

SwissTPH - Notice D.1: Formal Sector

Presentation: 

View file
nameSwissTPH openIMIS FS 09.2020.pptx

Time budget remaining and workload remaining:

Discussion:

Healthix

...

- Notice D.1: Formal Sector API

...

Presentation: 

Time budget remaining and workload remaining: waiting for contract

Discussion:

  • OpenHIM is being used for integration

Other Topics


Evaluation