The Release Cycle

openIMIS is released twice a year. The plan is to have a new release out in April and October every year. For each release cycle there is a fixed sequence of phases that the software has to pass:

Phase

Activities

April

October

Platform

Phase

Activities

April

October

Platform

Freeze

Feature freeze

end of February

end of August

Alpha

IT Testing

two weeks

Beta

Bug fix and implementers testing

one month

RC

Final release candidate

two weeks

GA

General availability - release date

by end of April

 

by end of October

 

The Release Roadmap

These are the timelines of the openIMIS releases:

Released Artifacts

Did you encounter a problem or do you have a suggestion?

Please contact our Service Desk